Heritage Site Service Station Upgrade for Long-Term Compliance

BP Welgelegen, Cape Town

BP Southern Africa appointed PetroENG to upgrade Welgelegen service station, delivering a full replacement of underground fuel lines, new dispensers, and environmental safeguards in 8 weeks.

The Challenge

Upgrade ageing infrastructure to ensure safe, compliant, and reliable operations while minimising downtime at a busy retail service station.

The Solution

PetroENG delivered civil & mechanical works:

  • Removed outdated steel fuel lines
  • Installed KPS underground fuel-resistant pipework
  • Integrated spil l containment with oily water separators
  • Executed concrete works and forecourt paving
  • Installed new fuel dispensers for improved reliability

Project Snapshot

  • Duration: 8 weeks
  • Full replacement of underground piping with modern KPS system
  • Environmental protection integrated through spill containment

Results & Impact

  • Improved compliance with modern underground fuel storage regulations
  • Enhanced safety and environmental safeguards wit h containment systems
  • Reduced risk of leakage or corrosion with advanced KPS pipework
  • Improved retail efficiency with new dispensers and forecourt works
  • Delivered upgrade within 8-week timeline, minimising operational disruption

Business Value

Delivered a modern, compliant, and
environmentally safe service station,
securing long-term operational
reliability for BP Welgelegen.

Timeline

8 weeks

Technologies

KPS underground fuel-resistant
pipework, oily water separators, spill
containment, new fuel dispensers,
reinforced forecourt concrete and
paving.

Key Features

Compliance with underground fuel
storage standards, environmental
protection, safety assurance, modern
fuel dispensing, minimal downtime
during upgrade.