PetroENG delivered a turnkey installation of a new Engen and Kaap Agric service station at Worcester Circle, completing full civil, mechanical, and environmental works in 12 weeks.
The Challenge
Construct a new retail fuel facility with modern compliance, environmental protection, and reliable service delivery standards.
The Solution
PetroENG delivered integrated construction and installation works:
- Installed 4 x 20 kl underground fuel tanks with compliant piping and fittings
- Installed oily water separators and full drainage pipework
- Constructed forecourt concrete with spill containment measures
- Installed fuel dispensers for retail operations
Project Snapshot
- Duration: 12 weeks
- 4 x 20 kl underground tanks installed
- Complete forecourt, drainage, and dispenser systems delivered
Results & Impact
- Delivered a fully operational and compliant retail service station within 12 weeks
- Enhanced environmental safeguards through spill containment and separators
- Improved retail efficiency with modern dispensers and piping systems
- Secured long-term operational reliability with compliant underground tanks
- Strengthened safety and compliance for both Engen and Kaap Agric operations
Business Value
Delivered a modern and compliant retail fuel station, ensuring environmental protection and reliable service for Engen and Kaap Agric customers.
Timeline
12 weeks
Technologies
4 x 20 kl underground tanks, compliant piping and fittings, oily water separators, drainage pipework, spill containment forecourt, fuel dispensers
Key Features
Regulatory compliance, environmental safeguards, modern retail infrastructure, safe and reliable fuel storage, fast-track delivery